Utilities Rehab Projects Update
Utilities Division - Feb. 24, 2012
The following streets will be closed during the week of Feb. 27 to allow for the repair or replacement of aging water and sewer pipes:
- Brent Street will be closed to through traffic between 644 and 800 Brent Street. This closure is expected to be in place for 3 weeks.
- Brookwood Drive will be closed to through traffic between Howell Street and Lakewood Drive. This closure is expected to be in place for two weeks.
- Greenway Avenue will be closed to through traffic between Glenn Avenue and 24th Street.
- Montrose Avenue will be closed to through traffic between Greenway Avenue and 24th Street.
For more information call CityLink 311.
|